As within this project i have pushed further ahead of my original plan, my revised timescale reads as spending:
3-4 days on cover generation
2 days on painting the studio for the show
1-2 days planning my space for the final year show
1 week on refinement and redrafts
2 days on assembly, scanning and oredering
2 days setting up space for show and moderation
2-3 days on infinity war advert
Total ~22 days
leaving a few weeks spread within for adjustments, reviews, blog alteration and editing.
3-4 days on cover generation
2 days on painting the studio for the show
1-2 days planning my space for the final year show
1 week on refinement and redrafts
2 days on assembly, scanning and oredering
2 days setting up space for show and moderation
2-3 days on infinity war advert
Total ~22 days
leaving a few weeks spread within for adjustments, reviews, blog alteration and editing.